Milan, 4 December 2019 – A2A was awarded the full capacity offered, equal to a total of 5 GW at the national level, in the second capacity market auction announced by Terna for the delivery year 2023. Of the 5 GW capacity offered, 0.2 GW regard newly implemented capacity. The auction award price was equal to €33,000/MW for the existing capacity and €75,000/MW for 15 years for the capacity to be implemented.
This result is in line with what the A2A Group attained in the auction with 2022 delivery.
The capacity market auctions are able to ensure the adequacy of the electricity system in the medium to long term and accelerate the energy transition to decarbonisation, as laid down in the Integrated National Plan for Energy and the Climate.